Steelhammer Road

Steelhammer Rd Project Update

Traffic Advisory Updates

During the project work hours (7am-5pm, Mon-Fri) traffic will be reduced to one lane with possible delays of up to 15 minutes. Drivers are strongly encouraged to utilize alternate routes. Additional traffic alerts will be provided on an as needed basis.

ROAD CLOSURE FOR PAVING IS SUBJECT TO CHANGE DUE TO WEATHER AND MATERIALS

REVISED DATES FOR ROAD CLOSURE - OCTOBER 23 & 24, 2017

Contractor Notice - Revised Dates for Steelhammer Paving  October 23-24, 2017

October 16 - 20, 2017 Steelhammer Closed for Paving - City Notification

October 16 - 20, 2017 Steelhammer Road Closure - Contractor Notice

Steelhammer Road Closure Aug. 7-11, 2017

Traffic Advisory - Work starts Monday, July 24th, 2017

September 25, 2017 Update

Storm Drainage line has been installed along the length of the project. The street has been widened. Curb edging is scheduled for the second week in October (weather permitting). The project is on schedule to be finished early November.

Steelhammer Road Improvements PH I

Project Background

The City's 2008 Transportation Master Plan recommended improving Steelhammer Road from Oak Street to Evans Valley Road. Phase I of the improvements will begin at Oak Street and travel south approximately 1,100 feet to Jaysie Drive. Pacific Excavation has been hired by the City to construct PH 1 of the Steelhammer improvements.

 PN 801 PH I Site Map Steelhammer Improvements Project

Project Benefits

  • Improved Roadway - Steelhammer Road will be widened to include two 11-foot wide travel lanes and two 5-foot wide bike lanes
  • Improved Pedestrian Features - Sidewalks and ADA ramps have been incorporated into the project design for improved pedestrian access and safety
  • Improved Infrastructure - The existing undersized storm drainage will be replaced with an improved 18-inch storm system. A cut-off trench and perforated pipe will be constructed at the bottom of Steelhammer to eliminate the problem associated with water seeping up through the asphalt. Existing fire hydrants will be relocated and or replaced, and water meters will be relocated behind the new sidewalk.

Project Schedule Overview

Work on the Steelhammer Road Improvement PH 1 project is scheduled to take place July 24 through November 24, 2017. All work is subject to change due to weather and other conditions.

Steelhammer Road Closure 8/7/17 - 8/11/17

Pacific Excavation Construction Notice 7/17/17

Contact Information

Project Manager:  John Cramer, Senior Engineer  503.874.2209  jcramer@silverton.or.us
                              Public Works Administration Office:  503.873.8679

Contractor:  Pacific Excavation - Eugene, OR

This page will be updated regularly throughout the project to provide schedule updates and project progress reports.