Capital Projects: PN22-1066 WWTP Blowers and Controls

Project Number: PN22-1066
Project Staff Contact: Bart Stepp
Project Type: Sewer Capital
Project Status: Under Construction
Location: Wastewater Treatment Plant, 400 Schemmel Lane. Google Maps                                                                                                                                                                         

Description:  Project will replace 3 existing blowers.  2 blowers will feed air to the aeration basins.  The 3rd blower will feed air to the post-aeration basin.  The project also includes the installation of new and additional instrumentation and programming of the instrumentation that will help better monitor the treatment process through the wastewater treatment plant.  Project has been awarded to contractor R.L. Reimers.  Due to the long lead time in procuring new blowers construction is not anticipated to start until fall of 2023.